LANE CLOSURES

Nightly lane and ramp closures are scheduled on northbound and southbound I-15, Monday, June 25 through Friday, June 29. At least one lane will remain open at all times.

Flaggers will direct traffic intermittently on Hidden Valley Parkway at I-15 during nighttime work.

The scheduled closures are:

Schedule Location
Monday, June 25 and
Tuesday, June 26
9 p.m. to 5 a.m. nightly
– Southbound I-15 from SR-60 to Second Street
– Hidden Valley Parkway northbound I-15 on- and off-ramp
Wednesday, June 27 and
Thursday, June 28
8 p.m. to 5 a.m. nightly
-Northbound & Southbound I-15 from SR-60 to Second Street
– Hidden Valley Parkway northbound I-15 on- and off-ramp
Friday, June 28
9 p.m. to 6 a.m.
-Southbound I-15 between SR-60 and SR-91
-Northbound I-15 between SR-91 and Second Street

***

Soundwall excavation work began this week on northbound I-15 between Ontario Ave. and the 91. Please be advised that this work may be noisy, due to equipment, back-up alarms, and other related construction activity. This work is expected to be intermittent for the next several weeks.


I-15 CLOSURES

Alternating northbound and southbound I-15 closures are scheduled for the City of Corona’s Cajalco Road Interchange Project later this month.

For a complete schedule and the latest updates, visit: i15cajalco.com

Neighboring Project

Cajalco Road / I-15 Interchange Improvement Project: Road work and closures may occur within the I-15 corridor as part of the City of Corona’s Cajalco Road / I-15 Interchange Improvement Project.  Click to view construction updates for this neighboring project or for more information, visit the project’s website at www.i15cajalco.com.



If information is needed in another language, please contact RCTC at (951) 787-7141 for free translation services.