Construction Update – Week of June 18

LANE CLOSURES

Nighttime lane closures are scheduled on northbound and southbound I-15 from Monday, June 18 to Friday, June 22 for placing k-rail, sawcutting, and paving on the roadway shoulder.  At least one lane will remain open at all times. The scheduled closures are:

Schedule Location
Monday, June 18
8 p.m. to 5 a.m.
– Southbound I-15 between SR-60 and SR-91
– Northbound I-15 between Cajalco Road and Second Street
Tuesday, June 19
8 p.m. to 5 a.m.
-Southbound I-15 between SR-60 and Cajalco Road
-Northbound I-15 between SR-91 and Second Street
Wednesday, June 20 –
Thursday, June 21
8 p.m. to 5 a.m. nightly
-Southbound I-15 between SR-60 and SR-91
-Northbound I-15 between SR-91 and Second Street
Friday, June 22
9 p.m. to 6 a.m.
-Southbound I-15 between SR-60 and SR-91
-Northbound I-15 between SR-91 and Second Street

***

Crews will begin assembling a paving machine in the roadway median next week. Paving will start soon in the median near Limonite Avenue.


WHAT IS THAT?

If you have been driving on the northbound I-15 near the Hidden Valley Parkway off-ramp, chances are you’ve noticed construction of a portable concrete mixing plant or batch plant.

The batch plant will mix the necessary supplies to create the concrete for the 15 Express Lanes. Having the source of the concrete close to the project site will reduce the number of concrete trucks necessary to be on the I-15 and adjacent streets.

The plant is expected to be completed next month, and a conveyor belt will be installed in the fall. The belt will transport the mixed concrete to the I-15 median, reducing the need for cement trucks to travel outside of the construction area.


15 FACTS ON THE 15 EXPRESS

Check out the latest video on the 15 Express Lanes, featuring information about the project’s soundwalls and the criteria for placing walls at specific locations.

 

 


I-15 CLOSURES

Alternating northbound and southbound I-15 closures are scheduled for the City of Corona’s Cajalco Road Interchange Project later this month.

For a complete schedule and the latest updates, visit: i15cajalco.com

Neighboring Project

Cajalco Road / I-15 Interchange Improvement Project: Road work and closures may occur within the I-15 corridor as part of the City of Corona’s Cajalco Road / I-15 Interchange Improvement Project.  Click to view construction updates for this neighboring project or for more information, visit the project’s website at www.i15cajalco.com.