I-15/LIMONITE INTERCHANGE

15 Express Lanes crews are on target to complete paving work in the Limonite Interchange area by the end of this month. The County of Riverside is then scheduled to begin work on the I-15/Limonite Avenue Interchange Project by the end of Sept. 2018. For more information about this project, visit the County of Riverside’s website.


LANE & RAMP CLOSURES

There will be weeknight lane closures throughout the project area on northbound and southbound I-15 between SR-91 and SR-60. Crews will be working between 8 p.m. and 5 a.m. nightly for paving, striping, setting k-rail and grinding.

At least one lane in each direction will remain open at all times.

Scheduled ramp closures include:

Schedule Location
Tuesday, Aug. 7
8 p.m. to 5 a.m.
– Northbound I-15: Hidden Valley
Pkwy off-ramp
– Northbound I-15: Second St. off-
ramp
Wednesday & Thursday, Aug. 8 -9
8 p.m. to 5 a.m. nightly
– Northbound I-15: Sixth St. off- and
on-ramps

Neighboring Project

Cajalco Road / I-15 Interchange Improvement Project: Road work and closures may occur within the I-15 corridor as part of the City of Corona’s Cajalco Road / I-15 Interchange Improvement Project.  Click to view construction updates for this neighboring project or for more information, visit the project’s website at www.i15cajalco.com.


If information is needed in another language, please contact RCTC at (951) 787-7141 for free translation services.