Construction Update – Week of Aug 20

Third Street in Norco

Third Street at the I-15 intersection in Norco will be reduced to one lane in each direction between 6:30 a.m. and 3:30 p.m. Monday, Aug. 20 through Friday, Aug. 24 for paving work. Motorists should use alternate routes if possible.


LANE & RAMP CLOSURES

Intermittent lane closures are scheduled at night on northbound and southbound I-15 for guardrail removal, shifting k-rail and grinding work. At least one lane in each direction will remain open at all times.

The scheduled closures are:

Schedule Northbound I-15 Southbound I-15
Monday, Aug. 20
8 p.m. to 5 a.m.
– Hidden Valley Pkwy to
Santa Ana River
– SR-60 to SR-91
Tuesday, Aug. 21
8 p.m. to 5 a.m.
– SR-91 to SR-60 – Santa Ana River to SR-91
– 15SB to 91WB Connector
– 15SB to 91EB Connector
Wednesday, Aug. 22
8 p.m. to 5 a.m.
— Magnolia Ave. to Bellegrave Ave. – Santa Ana River to SR-91
– 15SB to 91WB Connector
– 15SB to 91EB Connector
Thursday, Aug. 23
8 p.m. to 5 a.m.
– Magnolia Ave. to Santa Ana River
– EB91 to NB15 Connector
– WB91 to NB15 Connector
– Santa Ana River to
Hidden Valley Pkwy
Friday, Aug. 24
8 p.m. to 6 a.m.
 – Ontario Ave. to Santa
Ana River
– Santa Ana River to
Ontario Ave.

 


Neighboring Project

Cajalco Road / I-15 Interchange Improvement Project: Road work and closures may occur within the I-15 corridor as part of the City of Corona’s Cajalco Road / I-15 Interchange Improvement Project.  Click to view construction updates for this neighboring project or for more information, visit the project’s website at www.i15cajalco.com.


If information is needed in another language, please contact RCTC at (951) 787-7141 for free translation services.