The 15 Express Lanes Project Updates

    • 15 Express Lanes Construction Update – Week of April 23

      Alternating nighttime lane closures are scheduled next week on northbound and southbound I-15 between State Route 60 and the Santa Ana River. The lane closures are needed for shoulder paving, striping, sawcutting and installing k-rail. At least one lane will remain open during alternating lane closures. The outside lane (the lane closest to the shoulder) also […]

      Print Friendly, PDF & Email
    • RCTC – 15 Express Lanes Construction Update – Week of April 16

      Alternating lane closures are scheduled nightly on northbound and southbound I-15 from Sunday, April 15 to Friday, April 20. At least two lanes in each direction will remain open at all times. Northbound lane closures will take place nightly from 8 p.m. to 5 a.m. between the Santa Ana River and Bellegrave Avenue. Southbound lane […]

      Print Friendly, PDF & Email
  •  